Event planning Gantt chart starts with Concept Development for two weeks, completing by 2023-08-01. Venue Selection follows, critical for three weeks and linked to Concept Development. Budget Planning runs concurrently with Concept Development for four weeks. Vendor Coordination is crucial for five weeks, depending on the venue chosen. Marketing and Promotion span three weeks alongside Venue Selection. Design and Decor follow Vendor Coordination for four weeks. Entertainment Arrangements and Food and Beverage Planning run for three weeks each, intertwined with Design and Decor. Event Day occurs after one week of Food and Beverage Planning. Post-Event Evaluation lasts for two weeks immediately afterward. Wrap Up and Thank You Notes follow, also lasting for two weeks. The Event Conclusion milestone is set for 2023-12-15, marking the event's successful completion.

event-planning-gantt.png

Event planning diagram code in Gleek

/g Event Planning

    Concept Development

        Done

        2023-08-01

        2w

    Venue Selection

        Critical

        => Concept Development

        3w

    Budget Planning

        Active

        => Concept Development

        4w

    Vendor Coordination

        Critical

        => Venue Selection

        5w

    Marketing and Promotion

        Active

        => Venue Selection

        3w

    Design and Decor

        Active

        => Vendor Coordination

        4w

    Entertainment Arrangements

        Active

        => Design and Decor

        3w

    Food and Beverage Planning

        Active

        => Vendor Coordination

        3w

    Event Day

        Active

        => Food and Beverage Planning

        1w

    Post Event Evaluation

        Active

        => Event Day

        2w

    Wrap Up and Thank You Notes

        Active

        => Post Event Evaluation

        2w

    Event Conclusion

        Milestone

        => Wrap Up and Thank You Notes

        2023-12-15

About Gantt charts

Gantt charts, named after Henry Gantt, aid in project organization and monitoring, showcasing task timelines, durations, and overlaps. They're versatile tools used across industries, offering an overview of project lifecycles, beneficial for planning, resource allocation, and stakeholder communication. These charts assist in scheduling, dependency identification, and progress visualization, enhancing task management and resource allocation for effective project execution.

Similar gantt chart examples

Supply chain management gantt chart

Construction Project Management gantt chart

Website development gantt chart

Implementation plan gantt chart

School management system project gantt chart

Business plan gantt chart

App development project gantt chart

Research project proposal gantt chart

Marketing campaign gantt chart